The original delivery timeline of the submarines was from 2022 to 2028. However, the project ran into delays due to various issues. The first of these was the fallout of the pandemic in 2020. The second, more significant setback, was Germany’s refusal to transfer diesel engines for the submarines.
However, the PN opted to stick with the program and waited for China to certify its domestic CHD-620 diesel engine, which would be used in lieu of the German MTU powerplant.